Following quiz provides Multiple Choice Questions (MCQs) related to QC Framework. You will have to read all the given answers and click over the correct answer. If you are not sure about the answer then you can check the answer using Show Answer button. You can use Next Quiz button to check new set of questions in the quiz.
Q 1 - Which options can be used to submit defects from HP Sprinter to HP Application Lifecycle Management? (Select two.)
Smart Identification
Defect Checking
Smart Defects
Smart Defects Identification
Defect Reminder
Answer : D
Explanation
Smart Defects and Defects Reminder can be used to submit defects from HP Sprinter to HP ALM.
Q 2 - Which feature determines the good, bad, or warning level for a KPI
Answer : A
Explanation
Milestone determines the good, bad, or warning level for a KPI.
Q 3 - What does assigning each Test Set folder to a Cycle enable you to do?
D - Separate test sets that will be run during the same cycle and check the global requirements
Answer : A
Explanation
Group together test sets that will be run during the same cycle and analyze the progress of the cycle as you run your tests.
Q 4 - Which type of data from an Excel spreadsheet can be imported Into ALM? (Select three.)
Requirements
Tests
Test instances
Defects
Baseline
Test plan
Answer : B
Explanation
Requirements, Tests and defects can be imported to ALM via Excel plugin.
Q 5 - Which ALM feature enables you to calculate risks?
B - Analysis requirement management
Answer : A
Explanation
Risk-based management feature enables you to calculate risks.
Q 6 - The __________ feature enables you to calculate at which level to test each requirement, based on the nature of the requirement and the resources you have available.
A - Level-based quality management
B - Calculate-based quality management
Answer : C
Explanation
Risk-based quality management feature enables you to calculate at which level to test each requirement, based on the nature of the requirement and the resources you have available.
Q 7 - The typical application is too large to test as a whole. The Test Plan module enables you to divide your application according to ________
Answer : A
Explanation
The Test Plan module enables you to divide your application according to Functionality.
Q 8 - In the Test Plan module, you create ________ by selecting requirements to link to a test.
Answer : B
Explanation
In the Test Plan module, we create Requirements coverage by selecting requirements to link to a test.
Q 9 - The Requirement module field Direct Cover Status means
A - The current status of the requirement
B - The previous status of the requirement
Answer : A
Explanation
The Requirement module field Direct Cover Status means the current status of the requirement.
Q 10 - A follow up flag is specific to your user login name. Anyone else viewing the record does not see your follow up alert.
Answer : A
Explanation
A follow up flag is specific to your user login name and anyone else viewing the record does not see your follow up alert.