SAP PM Online Quiz



Following quiz provides Multiple Choice Questions (MCQs) related to SAP PM. You will have to read all the given answers and click over the correct answer. If you are not sure about the answer then you can check the answer using Show Answer button. You can use Next Quiz button to check new set of questions in the quiz.

Questions and Answers

Answer : E

Explanation

Maintenance plant for a technical object is known as plant in which you perform the maintenance tasks for the objects and planning is done. You can perform the following activities in Maintenance Planning Plant −

  • Defining Task list as per maintenance plan
  • As per BOM in task list, you perform material planning.
  • Management and scheduling of maintenance plans
  • Maintenance Orders creation and execution

Q 2 - In Preventive Maintenance, a multiple counter plan do not have their own maintenance strategy and have the cycle sets. They contain a combination of time-based and performance-based cycles?

A - True

B - False

Answer : A

Q 3 - Which of the following is used to define the sequence of activities that are performed as part of Preventive Maintenance in an organization?

A - Task Lists

B - Notification

C - Work Order

D - Maintenance Order

Answer : A

Q 4 - Which process of SAP Plant Maintenance is used to repair spare parts and to return the spare parts to warehouse or to the equipment?

A - Refurbishment Process

B - Project-Oriented Maintenance

C - Breakdown Maintenance

D - Preventive Maintenance

E - Work Clearance Maintenance

Answer : A

Explanation

Refurbishment is defined as process to repair spare parts and to return the spare parts to warehouse or to the equipment. You can define a Refurbishment order as Maintenance order by which you can execute the process of refurbishing damaged equipment and to perform this you need a material and Serial # combination.

Q 5 - In SAP PM, a new notification can be created with reference from?

A - Order

B - Technical object

C - Functional Location

D - All of these

E - a & b

Answer : D

Q 6 - To better manage and monitor Plant Maintenance process in Financial Management, you can integrate Plant Maintenance (PM) and Funds Management (FM)?

A - True

B - False

Answer : A

Q 7 - In SAP Plant Maintenance, Maintenance strategies are mandatory to define maintenance plans?

A - True

B - False

Answer : B

Explanation

Maintenance strategies are optional in Maintenance plans like multiple counter plan.

Q 8 - Which of the following shows an invalid warranty and negative checks are shown for Warranty claim results?

A - 00

B - 03

C - 01

D - 02

Answer : B

Explanation

  • 00 shows a valid warranty and positive check result are shown.
  • 03 shows an invalid warranty and negative check result are shown.
  • 01 shows no warranty check possible since required measuring point is missing in the warranty claim.
  • 02 shows no warranty check possible since required measurement document is missing in the system.

Q 9 - What is the usage type for BOMs in plant maintenance?

A - 1

B - 2

C - 3

D - 4

Answer : D

Q 10 - In SAP Plant Maintenance, which of the following role is responsible to perform planning maintenance tasks based on incoming malfunction reports and is responsible to raise maintenance orders, order type, scope, resources, and schedule of the tasks delivery?

A - Maintenance Manager

B - Maintenance Planner

C - Maintenance engineer

D - Maintenance Supervisor

Answer : B

Explanation

In SAP Plant Maintenance, a Maintenance planner is responsible for planning maintenance tasks based on incoming malfunction reports. Maintenance planner is responsible to raise maintenance orders, order type, scope, resources, and schedule of the tasks delivery.

sap_pm_questions_answers.htm