- SAP PP - Home
- SAP PP - Introduction
- SAP PP - Common Tables
- SAP PP - Organization Structure
- Integration with Other Modules
- SAP PP - Master Data
- SAP PP - Bill of Materials
- SAP PP - Work Center
- SAP PP - Routing
- SAP PP - Demand Management
- SAP PP - Creating PIR
- Material Requirement Planning
- SAP PP - MRP List
- SAP PP - Long Term Planning
- SAP PP - Production Orders
- SAP PP - Production Order Change
- Production Order Confirmation
- Canceling Production Order
- SAP PP - Capacity Planning
- SAP PP - Capacity Leveling
- SAP PP - Goods Receipt
- SAP PP - Stock Overview
- SAP PP - Goods Issue
- SAP PP - Goods Issue Reversal
- SAP PP - Lean Manufacturing
- SAP PP - Reports
- SAP PP - Material Document List
- Stock of Multiple Materials
- List in Bill of Material
SAP PP Online Quiz
Following quiz provides Multiple Choice Questions (MCQs) related to SAP PP. You will have to read all the given answers and click over the correct answer. If you are not sure about the answer then you can check the answer using Show Answer button. You can use Next Quiz button to check new set of questions in the quiz.
Q 1 - Which of the following module deals with processes like capacity planning and material planning and execution of production order, bill of material and goods movement?
Answer : D
Q 2 - In SAP Production Planning, how many BOMs can be created as per material type?
Answer : B
Answer : A
Q 4 - Which of the following Planning strategy is used to produce stock without Sales Order?
Answer : B
Q 5 - After MRP run, which of the following gets created in Planning?
Answer : A
Q 6 - Which of the following is performed using Planning table and orders are processed as define in work center to meet the Production process?
Answer : B
Explanation
Capacity leveling is performed for performing detailed production planning purpose. This is done through planning table which is used to carry detailed planning of capacity requirements over time in future.
Q 7 - Which of the following is used to generate static report that contains planning run material wise and it displays time of MRP run at the top?
Answer : A
Explanation
MRP List is used to generate static report that contains planning run material wise and it displays time of MRP run at the top.
Use T-Code MD05 or go to Logistics → Production → MRP → Evaluation → MRP list
Answer : B
Q 9 - To see real time stock, you can use this report for multiple material?
Answer : B
Explanation
To see real time stock, you can use this report for multiple materials. When goods movement are done, you can use this report to see real time stock information.
Use T-Code: MB52
Q 10 - To set your PIR version active, which of the below value should be used to specify requirement would be considered in material requirement planning?
Answer : A
Explanation
In SAP PP, demand management is performed by Planned Independent requirement PIR. Planned Independent requirement provides input for production planning. A PIR contains one planned quantity of product and one date for material or a planned quantity is split over a span of time period.
To set your PIR version active use value 00 to specify requirement would be considered in material requirement planning. To maintain number of versions of planned independent requirement, you can set some numbers to active and others to inactive.