Following quiz provides Multiple Choice Questions (MCQs) related to SAP PS. You will have to read all the given answers and click over the correct answer. If you are not sure about the answer then you can check the answer using Show Answer button. You can use Next Quiz button to check new set of questions in the quiz.

Questions and Answers

Q 1 - Arrange the below steps in correct order in Project implementation?

1. Create Project

2. Project Planning

3. Project Completion

4. Budgeting and Release

5. Project Implementation

6. Create Templates/WBS

A - 1,2,3,4,5,6

B - 6,1,2,4,5,3

C - 6,1,2,5,4,3

D - 6,1,4,2,5,3

Answer : B

Explanation

Below are the key steps involved in Project process flow:

  • Create Templates/WBS
  • Create Project
  • Project Planning
  • Budgeting and Release
  • Project Implementation
  • Project Completion

Q 2 - In Project system, it is also possible to assign any object currency to which of the following objects in the system?

A - WBS element

B - Project definition

C - Network header

D - Network activity

E - All of the above

Answer : E

Explanation

Object currency:

In Project system, it is also possible to assign any object currency to different objects in the system.

  • WBS element
  • Project definition
  • Network header
  • Network activity

Q 3 - Which of the following currency type costs and revenues are recorded as per currency of the business transaction?

A - Object Currency

B - Company Level Currency

C - Controlling area Currency

D - Transaction Currency

Answer : D

Explanation

Transaction currency:

In this case, you use the costs and revenues from different business transactions are recorded as per currency of the business transaction.

Example:

You can take the currency of PO in which it is raised in the system

Q 4 - Which of the following is used to define the work order that has a structure in common with production, maintenance and inspection orders?

A - Network

B - Production Order

C - Settlement Profile

D - None of the above

Answer : A

Q 5 - Which of the following organization element ae required for creation of project definition in SAP Project System?

A - Company Code

B - Controlling Area

C - Controlling Area and Plant

D - Controlling Area and company code

Answer : B

Q 6 - You should change the keys related to costing sheet or the results analysis key as these cant change existing system?

A - True

B - False

Answer : B

Q 7 - Where do you control the budget for the project in SAP PS system?

A - Project Profile

B - Settlement Profile

C - Cost Profile

D - Budget Profile

Answer : D

Answer : C

Q 9 - Consider a user A is assigned to user group 1 that has read authorization for a PS object and user has change authorization for PS object. The user gets?

A - Read Authorization

B - Change Authorization

C - Both of the above

Answer : B

Explanation

Consider a user A is assigned to user group 1 that has read authorization for a PS object and user has change authorization for PS object. The user gets change authorization in this scenario.

Q 10 - Which of the following is an engine which is used to fill demand and supply gap of material?

A - Plant Maintenance

B - Storage

C - MRP run

D - WBS

Answer : C

Explanation

MRP run or planning run is an engine which is used to fill demand and supply gap. Issues & Receipts are called MRP Elements.