SAP PS Online Quiz



Following quiz provides Multiple Choice Questions (MCQs) related to SAP PS. You will have to read all the given answers and click over the correct answer. If you are not sure about the answer then you can check the answer using Show Answer button. You can use Next Quiz button to check new set of questions in the quiz.

Questions and Answers

Q 1 - As per budget, a project related to Capital Investment is commonly?

A - Internal Project

B - External Project

C - Vendor Project

D - None of these

Answer : A

Explanation

Internal Financed Projects

This includes project related to capital investment or overhead cost projects.

Q 2 - In Project system, it is also possible to assign any object currency to which of the following objects in the system?

A - WBS element

B - Project definition

C - Network header

D - Network activity

E - All of the above

Answer : E

Explanation

Object currency:

In Project system, it is also possible to assign any object currency to different objects in the system.

  • WBS element
  • Project definition
  • Network header
  • Network activity

Q 4 - Which of the following information is maintained under project profile section?

A - Basic data

B - Time scheduling

C - Costs/revenues/finances

D - Organizational data

E - All of the above

Answer : E

Q 5 - In SAP Project System, how many levels of WBS elements can be created?

A - 255

B - 256

C - 999

D - 101

Answer : A

Q 7 - Where do you control the budget for the project in SAP PS system?

A - Project Profile

B - Settlement Profile

C - Cost Profile

D - Budget Profile

Answer : D

Q 8 - Using Control key in SAP PS system, you can determine the business transactions to be performed when you perform an activity?

A - True

B - False

Answer : A

Q 9 - Access control list function should be activated in project profile or network profile?

A - True

B - False

Answer : A

Explanation

In SAP Project system, you use access control list to assign authorizations for specific Project system objects. Access control list function should be activated in project profile or network profile.

Q 10 - In SAP PS, which of the following project version is used to store different cost plans for a project?

A - Project Versions

B - Plan Versions

C - Selection Versions

D - Simulation Versions

Answer : B

Explanation

There are different project versions types available in Project System:

Project Versions:

To compare project status at specific time period.

Plan Versions:

This is sued to store different cost plans for a project.

Selection Versions:

This is used to perform background processing and to save the project data matching certain selection criteria.

Simulation Versions

In below table, you can see the different features in a project that above versions supports in SAP system.