- SAP SCM - Home
- SAP SCM - Overview
- SAP SCM - Components
- SAP SCM - Benefits
- SAP SCM - Demand Management
- SAP SCM - Creating PIR
- Material Requirement Planning
- SAP SCM - Planned Order Creation
- Production Order Creation
- SAP SCM - Goods Issue
- Production Order Confirmation
- Production Order Cancellation
- SAP SCM - Integration
- SAP SCM - Integration Models
- SAP SCM - Master Data
- SAP SCM - Resources
- Production Data Structures
- Transfer Changed Master Data
- SAP SCM - Transfer Changed BOMs
- SAP SCM - Models and Versions
- SAP SCM - Applications
- Advanced Planning Optimization
- SAP SCM - Extended Warehouse
- Transportation Management
- Supply Network Collaboration
- Forecasting & Replenishment
- Consultant Responsibilities
SAP SCM Online Quiz
Following quiz provides Multiple Choice Questions (MCQs) related to SAP SCM. You will have to read all the given answers and click over the correct answer. If you are not sure about the answer then you can check the answer using Show Answer button. You can use Next Quiz button to check new set of questions in the quiz.
Q 1 - Which of the following is not a key attribute of Supply Chain Management process?
Answer : D
Q 2 - In a manufacturing enterprise, which of the following is not a part of Internal Supply chain management?
Answer : C
Q 3 - Which of the following is/are benefits of Supply Chain Management process?
B - To effectively manage forecasting and handling sudden changes in demand and supply process.
C - To effectively use Net Fixed assets NFA like plants and equipment.
Answer : E
Answer : B
Explanation
NetChange in planning horizon −
This run considers the requirement in predefined planning horizon and not like net change which check the future requirements.
In this run, system consider only those material which has undergone some changes from their last MRP run.
Answer : B
Explanation
You can create up to 99 Bills of Material.
Answer : A
Answer : B
Q 8 - Which of the following is not a member of SCM process normally?
Answer : D
Q 9 - When a model is deleted, it also remove all the planning versions that has been created for the model?
Answer : A
Explanation
You can also delete model/planning version. If you have the authorization to delete. When a model is deleted, it also remove all the planning versions that has been created for this model.
Q 10 - When goods are issued, system decreases the inventory of components at the storage location in Production Planning system?